New Murabba and the Mukaab: excavation and piling done, main works next
The New Murabba project has dug out the Mukaab site and driven its piles. The main construction contract is the next step to watch; the cost and final spec are not yet published.
The ground at New Murabba has been dug out and the Mukaab's piles are in. The next step is the main works contract for the 400 m cube itself. The official figures for the wider project have been updated several times since launch.
| Figure | Value | As of | Source |
|---|---|---|---|
| Earth moved | 15M+ m³ | 1 Dec 2025 | Developer |
| Foundation piles completed | 1,226 | FY2025 | PIF Annual Report 2025 |
| Mukaab main works award | none announced | to Aug 2026 | Developer, May 2024 tender statement |
| Residential units, launch vs now | 104,000+ vs 90,000+ | Feb 2023, Mar 2026 | PIF, SPA |
| Published completion date | 2030 (project), end-2032 (stadium) | 2023 and 2024 | PIF, SPA |
| Official capital cost | not published | to Aug 2026 | none exists |
The excavation is close to done
New Murabba sits at the junction of King Salman Road and King Khalid Road in north-west Riyadh. PIF launched it in February 2023, with the Mukaab at its centre: 400 m high, wide and long.
The digging went fast at first, from about 2 million m³ in December 2023 to about 10 million m³ by October 2024. The developer called that 86% of the excavation. PIF's 2024 annual report gave 13.1 million m³ for the year. After that the pace slowed, reaching 15 million m³ by December 2025. With most of the hole already dug, a slow finish is what you would expect.
PIF's 2025 annual report adds 1,226 foundation piles. The number the structure needs is not published, so we can't turn that into a percentage.
The main works contract comes next
In May 2024 the developer said that year would bring piling and the tender for the raft foundation and main works. Piling went to HSSG Foundation Contracting that month (SPA). The main works award has not been announced yet.
The other contracts signed so far cover preparation and advice. Bechtel and Turner Arabia manage the project, China Harbour did the earthworks, and in January 2026 an AECOM-Jacobs joint venture took on design across the district. The chart shows the order.
How the official unit count has been updated
At launch PIF gave more than 104,000 homes. A developer presentation in March 2024 said 119,000. Statements between late 2024 and early 2025 used 100,000. In March 2026 the state news agency put it at over 90,000 (SPA). The same release gave a site of 14 million sqm for over 280,000 residents.
Retail and office areas have been updated too, and some developer pages still show earlier figures. Our reading is that site area and floor area are sometimes quoted on different bases.
Published dates
PIF's 2030 completion date from 2023 remains the published target. The other date is end-2032 for New Murabba Stadium, one of 15 venues for the 2034 World Cup. The main works award will be the first published milestone for the Mukaab structure itself. The stadium has an outside deadline, so it is the more likely first delivery.
A capital cost has not been published. The figure that circulates comes from a brokerage estimate and we don't use it.
What to watch
The next real signal is the Mukaab main works award. Until it appears, buyers and sub-developers should treat any date for the cube as a target. The developer says 60% of the downtown will be built by sub-developers (developer), most of them not yet named.
For the full dated record of specs and contracts, ask for the New Murabba ledger.
Sources
- PIF, New Murabba launch release, 16 February 2023 (Wayback capture 18 August 2026): link
- SPA, New Murabba at MIPIM 2026, 15 March 2026: link
- SPA, Mukaab piling contract with HSSG, 23 May 2024: link
- SPA, New Murabba Stadium as a World Cup 2034 venue, 12 December 2024: link
- PIF Annual Report 2024 (13.1M m³ excavation): link
- PIF Annual Report 2025 (1,226 piles): link
- New Murabba, May 2024 Mukaab tender statement: link
- New Murabba, October 2024 progress release (86% excavation): link
- New Murabba, December 2025 release (15M+ m³): link
- New Murabba, Bechtel agreement, 27 August 2023 (capture 18 January 2026): link
- New Murabba, Turner Arabia agreement, 3 September 2023: link
- New Murabba, China Harbour earthworks contract, 15 October 2023: link
- New Murabba, AECOM-Jacobs JV, 22 January 2026: link
- New Murabba partnership page (60% for sub-developers): link